Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Shawnigan group challenging assessments, claiming soil dumps have lowered values

Neighbours raise water quality, property value issues

Editorial: Curbing urban sprawl a laudable goal

We did not agree with the motion put forward to put a moratorium on development.

Lake Flashback: Haiti relief pours in, political kerfuffle has deep roots, and BCFP acts quickly on PCP leak

We’ve also included a picture of Lake Cowichan Kinsmen rescuing the Duckpond dock

Chris Wilkinson column: Perspective matters now more than later

The point here is that priorities matter. All the time. Every month.

Flooding has closed several roads in Cowichan Valley

All the usual suspects are involved: overflowing ditches, low-lying spots, and huge piles of snow

VIDEO: Rare ‘ice circle’ spotted on Kamloops river

An ice circle or ice pan, has formed in the chilly waters just east of the Yellowhead Bridge

Uber, Lyft approved for ride-hailing in Lower Mainland

Kater Technologies Inc.’s application was rejected

B.C. man rescued after getting trapped headfirst in well as water level rose

The rescue involved crews from Oak Bay and Saanich

Investigators in wildfire-torn Australia head to site of B.C. airtanker crash

The B.C. government sends condolences to Port Alberni-owned Coulson Aviation

RCMP investigating sexual allegation against Lower Mainland police officer

Delta officer suspended while the alleged off-duty incident involving a co-worker is investigated

Former Mountie, sports coach convicted of sex abuse in B.C. granted day parole

Alan Davidson was sentenced to almost six years for abusing seven boys in the late 1970s and early 1990s

VIDEO: Person in wheelchair narrowly avoids collision with car in Kelowna

There were no injuries in the scary looking near-accident last week in Rutland

Here’s what Canada is doing to stop the coronavirus from getting in

Health officials are monitoring multiple possible cases in Canada

Most Read