The Trans Mountain expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C. (Canadian Press file images)

Trans Mountain pipeline expansion cost jumps 70% to $12.6 billion

The estimate of $7.4 billion was made in 2017 by the previous owner

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

ALSO READ: Opponents in B.C. to ramp up protests against Trans Mountain pipeline

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.

Opponents of the pipeline expansion have vowed to do whatever it takes to stop the project despite losing a legal challenge before the Federal Court of Appeal earlier this week.

The four First Nations who lost the court challenge on Tuesday have 60 days to seek leave to appeal to the Supreme Court of Canada.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Pumps not needed on the Cowichan River this year

Wet year so far has resulted in higher water levels

Pig destined for sanctuary goes missing from Cobble Hill farm

Berleen was less than two weeks from travelling to Manitoba when she vanished

Editorial: Mask wearing: innocuous advice has turned into polarizing war

Somehow, this innocuous recommendation has become a polarizing war for some.

UPDATED: Young deckhands backed out of fatal Arctic Fox II trip just before fishboat departed

Inexperienced twin brothers had ‘gut feeling’ and bailed before going to open ocean

578 British Columbians currently infected with COVID-19

Seventy-eight new cases confirmed in past 24 hours

Captive fawn seized from Island home

Valley resident charged and fined under the Wildlife Act

Pandemic could be driving more parents to get on board with flu shot: study

University of B.C. study gauges willingness for parents to vaccinate children for influenza

Watchdog clears Okanagan RCMP in death of man after arrest over alleged stolen pizzas

The man died in hospital after having difficulty breathing and broken ribs

Have you seen Berleen? B.C. pig destined for sanctuary goes missing

Berleen was less than two weeks from travelling to Manitoba when she vanished

Health Canada says several kids hospitalized after eating edible pot products

People warned not to store cannabis products where children can find them

‘It’s not just about me’: McKenna cites need to protect politicians from threats

Police investigation was launched after someone yelled obscenities at a member of McKenna’s staff

Michigan plans dedicated road lanes for autonomous vehicles

First study of its kind in the U.S. to figure out whether existing lanes or shoulders could be used

Most Read