The CVRD’s finance manager Natalie Wehner delivered a report to the board outlining the status of 81 capital projects in the district, and detailed which ones may face delays due to COVID-19 and other snags. (File photo)

The CVRD’s finance manager Natalie Wehner delivered a report to the board outlining the status of 81 capital projects in the district, and detailed which ones may face delays due to COVID-19 and other snags. (File photo)

CVRD may have to delay 11 capital projects scheduled for 2020

More than 50 of the 81 projects are complete or are schedule for the year

The approximately $5.9-million Mill Bay sewer project that was scheduled to be completed in 2020 could be postponed.

It’s among a substantial list of projects whose immediate future is up in the air. The Mill Bay sewer project has hit delays in the project’s timeline due to the ongoing COVID-19 crisis, and the approval process for the project to proceed.

A staff report from Natalie Wehner, the Cowichan Valley Regional District’s financial director, outlining the status of the 81 capital projects included in the CVRD’s budget for 2020, states that 41 of the projects are on track to be completed on schedule this year, 18 have not yet begun, 10 are complete, 11 could possibly have to be delayed and one will not be completed this year.

RELATED STORY: CVRD RECEIVES AWARD FOR ANNUAL FINANCIAL REPORTING

Approximately 24 per cent of the CVRD’s $100 million budget in 2020 is for capital projects approved during the 2020 budget deliberations, or carried forward from previous years’ budgets.

“Potential delays are due to staff time, availability of materials, potential consideration of changes to the projects and requirements for electoral approval of borrowing bylaws,” Wehner said in the report.

“The one project that will not be complete [a $20,000 well rehabilitation project at the Dogwood Ridge water system] is due to considerations of funding options and whether it would be more advantageous to save up the funds or borrow to pay for the project.”

Wehner reported that the $3.7-million water treatment upgrade of the Saltair water system could possibly be delayed because authorization of the loan needed for the project to proceed requires an alternative approval process to be held to determine if the electorate wants to borrow for it.

An AAP requires that 10 per cent or more of eligible voters must sign and submit response forms in opposition to the project to stop the borrowing process from proceeding.

RELATED STORY: COUNCIL CHOOSES AAP OVER REFERENDUM TO GET VOTER APPROVAL ON NEW RCMP DETACHMENT SPENDING

The $2-million water treatment upgrade at the Shawnigan Lake North water system may also be delayed, also due to the need for loan authorization and an AAP, and the new $300,000 water reservoir at the Mesachie Lake water system could be postponed because road work is required in the summer months for access to the site.

A $230,000 collection system upgrade at the Cowichan Bay sewer system, a $124,000 upgrade at the Shawnigan Beach Estates sewer system, and a $100,000 upgrade at Eagle Heights sewer system may also be delayed due to the need for further investigation of the projects.

RELATED STORY: CVRD TO RECEIVE ALMOST $8 MILLION FOR WATER PROJECTS

A $35,000 upgrade at the Youbou water system, and a $20,000 generator project at the Buena Vista Place in the Cowichan Bay sewer system may also have to be delayed because of the lack of availability of electricians.

The CVRD is also reconsidering a $30,000 project for outdoor fitness equipment at Kerry Park.



robert.barron@cowichanvalleycitizen.com

Like us on Facebook and follow us on Twitter

municipal politics

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

A picture of Bug before the attack by the dogs on Nov. 17, 2020. (Submitted photo)
Three dogs almost kill cat in Miller Road area near Duncan

Efforts to catch the canines unsuccessful so far

Beautiful morning with the sun peaking through, as viewed from Thetis Island. (Photo by Kelly Bannister)
November characterized by a record high, no snow and plenty of rain in Chemainus region

Temperature almost hits the 20 degree Celsius mark on Nov. 4

Group wants to start a pilot program for regenerative farms in North Cowichan. (File photo)
Group looks to North Cowichan for farmland

Land could also be used for affordable housing

The CVRD will reconsider its policies on fireworks after receiving complaints. (File photo)
Cowichan Valley Regional District considers options for fireworks after receiving complaints

Distict only allows fireworks on Halloween and New Year’s Eve, with a permit

Ben Maartman, left, and Murray McNab are running for regional director for Area H North Oyster-Diamond in a Cowichan Valley Regional District byelection later this month. (Photos submitted)
Preliminary Area H byelection results show Maartman up by seven votes, McNab to ask for recount

Results of the by-election to by finalized by noon on Tuesday, December 1

A tongue-in-cheek message about wearing a face mask to curb the spread of COVID-19 on a sign outside a church near Royal Columbia Hospital, in New Westminster, B.C., on Sunday, Nov. 29, 2020. THE CANADIAN PRESS/Darryl Dyck
B.C.’s COVID-19 infection count climbs back up to 656

20 more people in hospital, active cases still rising

Dave Wallace coached the Parksville Royals for 23 years. (PQB News file photo)
B.C. baseball community mourns death of legendary Vancouver Island coach Dave Wallace

‘All who knew Dave and his passion for the game will miss him greatly’

THE CANADIAN PRESS/Nathan Denette
B.C. researchers launch study to test kids, young adults for COVID-19 antibodies

Kids and youth can often be asymptomatic carriers of the novel coronavirus

A sign is seen this past summer outside the Yunesit’in Government office west of Williams Lake reminding visitors and members to stay safe amid the COVID-19 pandemic. (Rebecca Dyok photo)
B.C. First Nation leaders await privacy commissioner decision on COVID-19 information

Release of life-saving data cannot wait, says coalition of First Nations

MLA Jennifer Whiteside is B.C.’s new minister of education. She is speaking out against Chilliwack school trustee Barry Neufeld and asking him to resign. (Black Press)
New education minister calls on Chilliwack trustee to resign

Whiteside echoes former minister’s promise to look at options to remove Barry Neufeld

Peter Beckett. ~ File photo
Supreme Court of Canada to decide if it will hear appeal in 2010 wife murder trial

Peter Beckett has stood trial twice for murder in connection with the death of his wife, Laura Letts-Beckett

Tabor Home in Abbotsford. (Ben Lypka/Abbotsford News)
B.C.’s largest COVID-19 care-home outbreak records 19 deaths, 147 cases

Tabor Home in Abbotsford has been battling outbreak since Nov. 4

Most Read