A timeline of events in British Columbia’s Site C dam project

Site C will go ahead, one year later and $5.3-billion more, the NDP announced Feb 26

A chronology of events in British Columbia’s Site C hydroelectric dam project:

Late 1950s: The location for a third dam on the Peace River is first looked at after the locations of WAC Bennett Dam and Peace Canyon Dam were identified.

1970s: Engineering work is done to determine the feasibility of a third dam.

1989: Plans for Site C are shelved because of local opposition to the project.

March 2001: The chairman of BC Hydro says he would like to see the project revived and get fast-track approval from the government.

April 2004: BC Hydro includes Site C in a package of initiatives it is studying to boost the province’s long-term supply of hydroelectricity.

December 2007: Preliminary cost estimates for Site C show the project could cost between $5 billion and $6.6 billion, doubling previous estimates by the province.

April 2010: The B.C. government announces a plan to build Site C.

December 2013: Public hearings begin on the project.

May 2014: A joint review panel gives no clear yes-or-no answer but says B.C. will need new energy at some point. It says the project would cause significant adverse effects on the environment and wildlife, as well as Indigenous communities and farmers in the area.

October 2014: Provincial and federal environmental certificates are issued.

December 2014: The B.C. government makes the decision to go ahead with construction.

July 2015: Construction begins on Site C.

July 2015: The B.C. Supreme Court dismissed a petition by the Peace Valley Landowner Association challenging provincial environmental approval of Site C. An appeal was dismissed in September 2016.

August 2015: The federal court dismissed an application by Prophet River First Nation and West Moberly First Nations challenging environmental approval of Site C by the federal government. An appeal was dismissed in January 2017.

February 2016: A judge orders protesters to leave their tent camp near the construction site after BC Hydro asked for an injunction.

December 2016: The government says the project is on schedule and on budget.

March 2017: The government says more than 2,000 workers are employed at Site C.

Aug. 2, 2017: The province’s newly sworn-in NDP government asks the B.C. Utilities Commission to review the project as it considers cancelling or delaying its construction.

Aug. 28, 2017: A United Nations panel says construction of the dam should be stopped until there is a full review of how it would affect Indigenous land.

Nov. 1, 2017: The B.C. Utilities Commission says the project is over budget and behind schedule in its report to the government, which promises a decision on Site C’s future by the end of the year.

Dec. 11, 2017: Premier John Horgan says the dam will be completed but the price tag is expected to rise from $8.3 billion to $10.7 billion.

July 31, 2020: Energy Minister Bruce Ralston asks for an independent analysis of the project from former deputy finance minister Peter Milburn after BC Hydro identifies problems with the project in an update to the B.C. Utilities Commission, including the need to improve its foundations to increase stability below the powerhouse, spillway and core areas of the dam.

Sept. 28, 2020: A former president of BC Hydro is among 18 prominent Canadians who urge the province to stop work on the project while geotechnical problems are explored.

Feb. 26, 2021: Horgan announces the project’s cost has grown to $16 billion, and it won’t be completed until 2025.

RELATED: B.C. to go ahead with Site C dam, with new $16B budget and delayed to 2025

RELATED: Open letter urges B.C. to pause work at Site C dam to review costs, geotechnical issues

Site C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

North Cowichan councillor Kate Marsh. (File photo)
North Cowichan postpones decision on cell tower placement

But cell tower policy may be developed soon

B.C. provincial health officer Dr. Bonnie Henry speaks at a press conference Monday, April 18. (B.C. Government image)
New COVID-19 cases tick down on the central Island

New cases held to single digits three days in a row

CVRD offices on Ingram Street will remain closed for another 14 weeks after flooding last month. (File photo)
CVRD headquarters closed for another three and a half months

Building significantly damaged during water leak

Victoria police are asking for help locating high-risk missing man Derek Whittaker, last seen in Victoria April 12. (Courtesy of VicPD)
MISSING: Police searching for Derek Whittaker, last seen in Victoria

Whittaker believed to be driving 1994 red Volkswagen Golf

The IIO is investigating after a police dog bit a man during a traffic stop near Ladysmith on April 17, 2021. (Black Press Media stock photo)
IIO investigating after police dog bites man near Ladysmith

RCMP dog bit man during traffic stop on Friday, April 17

FILE – NDP Leader John Horgan, right, and local candidate Mike Farnworth greet one another with an elbow bump during a campaign stop in Coquitlam, B.C., on Friday, September 25, 2020. THE CANADIAN PRESS/Darryl Dyck
B.C. won’t be using random individual road stops to enforce travel rules: Safety Minister

Minister Mike Farnworth says travel checks only being considered at major highway junctions, ferry ports

..
Abbotsford nurse at ‘breaking point’ pleads with public to take COVID-19 seriously

Instagram post urges general population to stay home, wear a mask and get vaccinated

Alex Mah of Chemainus spends a sunny day at Kin Beach reading to daughter Beatrice Mah. 3. (Photo by Don Bodger)
Vancouver Island’s mini-summer poised to fade

Cooler and damper this weekend, summer-like conditions not likely to return until late June

A native-to-B.C. wild queen bee (bombus melanopygus for those in the know) feeds on a periwinkle flower. (Submitted/Sarah Johnson, Native Bee Society of BC)
B.C.’s wild bees need messy gardens to survive

The year-long nesting period makes habitat a primary concern for wild bees

Nanaimo Fire Rescue investigator Mark Jonah probes the scene of a blaze that destroyed two apartments on Sunday, April 18. The cause of the blaze has not been determined. (Chris Bush/News Bulletin)
Arson suspect arrested after apartment fire in Nanaimo

35-year-old man arrested for allegedly starting fire lived in the complex

A wildfire has started near Gold River, and B.C. Wildfire Service crews are on scene. Photo courtesy Coastal Fire Centre
Small wildfire burning in difficult terrain near Gold River

Coastal Fire Centre investigating, but confirms blaze is human-caused

FILE – Health-care workers wave to people clapping and yelling thank you to the frontline workers during the 7 p.m.-tribute outside the Lions Gate Hospital in North Vancouver, B.C. Wednesday, April 8, 2020. THE CANADIAN PRESS/Jonathan Hayward
B.C. nurses issue plea for all to follow health orders as hospitalizations spike

Nurses worried about strain COVID-19 is having on hospital capacity, care

University of Victoria rowing coach Barney Williams is photographed in the stands during the Greater Victoria Invitational at CARSA Performance Gym at the University of Victoria in Victoria, B.C., on Friday, November 29, 2019. The University of Victoria says Williams has resigned effective immediately. (THE CANADIAN PRESS/Chad Hipolito)
University of Victoria women’s rowing coach resigns by mutual agreement

Lawsuit filed last summer accused Barney Williams of verbal abuse

Most Read