Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Drivesmart column: Where are the corners of your vehicle

We were expected to drive as fast as we were able to in addition to leaving all the cones alone.

Cowichan Coffee Time: Lots of winners honoured, and volunteers step up

• Members of 4-H have been busy lately, with numerous competitions. Cowichan… Continue reading

Robert Barron column: Opioid crisis hits home, literally

I found two fire trucks and two ambulances parked in my driveway and along the adjacent street

Huge demand for spot prawns, limited supply for Cowichan

Most of the more than 200 boats harvesting spot prawns freeze their catch and ship it away.

Andrea Rondeau column: Positives on the environmental front

Does hearten me so many people concerned about future of environment they’re taking it to the polls.

UPDATE: B.C. pilot killed in Honduras plane crash

The crash happened in the Roatan Islands area, according to officials

Carbon dioxide at highest levels for over 2.5 million years, expert warns of 100 years of disruption

CO2 levels rising rapidly, now higher than at any point in humanity’s history

RCMP arrest violent offender on Vancouver Island

Police struggle with suspect and take him down with a taser

B.C. ferry stops to let black bear swim past near Nanaimo

Queen of Oak Bay brakes for wildlife in Nanaimo’s Departure Bay

Mother dead, child in critical condition after carbon monoxide poisoning at Shuswap campground

The woman was found unresponsive insider her tent and the youth was taken via air ambulance to hospital

Canada’s parole officers say correctional system has reached breaking point

About half of Canada’s federal parole officers work inside penitentiaries and correctional institutions

Montreal researchers create audible hockey puck for visually impaired players

Three years ago, Gilles Ouellet came up with the idea for a puck that makes a continuous sound

Vancouver Island MusicFest: ‘House bands’ from the golden age of rock and R&B

Some of America’s greatest session musicians are coming to the Comox Valley this summer

Former B.C. Greyhound bus drivers head to Penticton for goodbye party

Big bash runs until Sunday, funded by drink cans left behind on busses over the years

Most Read