B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Police and fire crews at work at a fire scene at Mount Prevost School (Kevin Rothbauer/Citizen)
Classes cancelled for Mount Prevost students today

Second school fire in five days for North Cowichan schools

New well in Youbou expected to meet community;s drinking water needs for years. (File photo)
New well provides fresh water in Youbou

Well expected to meet community’s needs for years

Smaller egg farmers find themselves in a David and Goliath situation when it comes to major producers and chain-grocery store shelf space. (Citizen file)
Name on the egg carton not what it seems, cautions Cowichan producer

“Island” eggs may come from Manitoba, Woike says

The Kerry Park Islanders and Peninsula Panthers battle during a Vancouver Island Junior Hockey League game in November 2020. (Kevin Rothbauer/Citizen)
Vancouver Island Junior Hockey League hasn’t given up on season

Games can’t resume until at least February, but league brass still hopeful

A woman wears a face mask and shield to curb the spread of COVID-19 while walking in North Vancouver, B.C., on Wednesday, January 6, 2020. THE CANADIAN PRESS/Darryl Dyck
536 COVID cases, 7 deaths reported as B.C. finds its first case of South African variant

Henry said 69,746 people have received their first dose of the COVID vaccine.

Nanaimo RCMP seek public assistance after numerous tire slashings between Jan. 12-14. (News Bulletin file)
Police seek public’s help after ‘tire slashing spree’ in central Nanaimo

Ten reports of slashed tires in the last three days, say Nanaimo RCMP

Prime Minister Justin Trudeau listens to a question during a news conference outside Rideau cottage in Ottawa, Friday, January 8, 2021. THE CANADIAN PRESS/Adrian Wyld
Trudeau says Canada’s COVID vaccine plan on track despite Pfizer cutting back deliveries

Canadian officials says it will still likely receive four million doses by the end of March

Letisha Reimer died Nov. 1, 2016 after being stabbed at Abbotsford Senior Secondary.
No evidence that killer was in ‘psychotic state’ during Abbotsford school stabbing: Crown

Second day of closing arguments at ‘not criminally responsible’ hearing for Gabriel Klein

Seiners fill the waters between Comox and Nanoose Bay during roe herring fishery. file photo, Pacific Wild
Quota debate heats up on the eve of Vancouver Island herring fishery

Industry and conservationists weigh in how much catch should be allowed as DFO decision coming soon

Alan Davidson was sentenced to almost six years for abusing seven boys in the late 1970s and early 1990s. (Canadian Press file)
Full parole granted to former Mountie, sports coach convicted of sex abuse of boys

Alan Davidson convicted of abusing boys in B.C. and Saskatchewan in late ’70s, early ’90s

The first COVID-19 vaccine arrives in B.C. in temperature-controlled containers, Dec. 13, 2020. (B.C. government)
More vaccine arrives as B.C. struggles with remote COVID-19 cases

Long-term care homes remain focus for public health

Most Read